Overdue fire safety actions on Harlow council homes fell from 2,487 to 1,648 in September. Cabinet is asked to approve £15m of fire safety work on 19 November.

Harlow Council closed 955 fire safety actions on its housing in September. The number of overdue actions fell from 2,487 at the end of August to 1,648 at the end of September, a drop of about a third.

The figures are in the council’s monthly housing compliance report. It goes to Cabinet on Thursday 19 November, moved from 12 November. The same meeting is asked to approve £15 million of new fire safety contracts.

Water safety is moving more slowly. At the end of September, 849 of the 1,964 council homes that need a legionella risk assessment still did not have a valid one.

Fire safety: where the backlog stands

Every fire risk assessment can raise actions, from a door closer to fire stopping in a loft. All 3,469 homes in scope had a current fire risk assessment in September. The work they raised is what has been running late.

At the end of September, the data tables show:

August September
Open actions 2,798 1,931
Overdue 2,487 1,648
Overdue and high risk 403 368
High risk, overdue by more than 12 months 210 189

Almost all of September’s progress came on low-rise blocks, under 11 metres tall. They had 904 actions closed in the month. They still hold most of what is late: 1,462 of the 1,648 overdue actions, and 350 of the 368 high-risk ones.

Bar chart of overdue fire safety actions on Harlow council housing at the end of September 2026 by building type: low rise 1,462, sheltered 74, high rise 71, medium rise 41. Total 1,648.
Overdue fire safety actions by building type, end of September 2026. Chart by Harlow Online
Share this chartFacebookWhatsAppX

The council now says it will close all overdue actions within three months. Last month’s report gave four. A further 413 open actions are parts an assessor judged could be replaced in the planned works programme for 2026 to 2027, down from 868 in August.

Separately, about 280 fire risk assessments have recommended a closer check of a building’s external walls, for cladding, balconies or combustible material. 65 of those checks are done, up from 55. The council says a recommendation “does not in itself indicate the presence of an identified life safety risk”. (Social housing compliance report, November 2026)

£15 million of fire safety work for Cabinet to approve

A separate contract award report asks Cabinet to award a district-wide programme of fire risk assessment repairs. It covers fire doors, fire stopping, loft and roof-void compartmentation, cavity barriers and fire-rated glazing. Three firms would share it, each with a contract worth £5 million including VAT (£4,166,667 before VAT):

  • Infinity Fire Prevention Ltd
  • Sureserve Compliance Fire Ltd
  • Bell Group Ltd

The same report asks to extend three existing contracts:

Contractor Work Extra New value
PRB Estate Ltd Urgent high-risk fire safety actions until the new contracts start £800,000 £3,275,000 including VAT
J&J Windows and Doors Limited Communal and front door replacements found in fire risk inspections £500,000 £1,673,842 plus VAT
Lura Construction Limited Bringing forward defective roofs from the 2027 to 2028 programme £800,000 £2,409,800.28 plus VAT

The report says the extensions cover “an unforeseen capacity gap”. The bid scores and prices are in appendices kept private for commercial reasons. The work is part of the council’s £162 million housing capital programme for 2026 to 2028.

Water safety: 849 homes still without a valid check

A legionella risk assessment checks a water system for the conditions that let the bacteria behind Legionnaires’ disease grow.

In September the council completed 128 assessments. That took compliance from 53.46% to 56.77%: 1,115 of 1,964 homes in scope. Last month’s report said all outstanding assessments were “targeted for completion” by mid-October.

The new report gives 191 assets with outstanding assessments at the end of September. It then says “performance reaching 100% during October”. The October figures will be in December’s report.

The repairs those assessments asked for are further behind:

  • 1,225 water safety remedial actions overdue, down from 1,338
  • 198 of them high risk
  • 498 more than 12 months overdue, including 17 high-risk actions

The council says communal water tanks are inspected every six months. It also says the single-supplier contract it had proposed for water hygiene “was not approved”, and that other options are being drawn up.

The rest of the September figures

  • Gas: 100%, with 935 servicing visits in the month
  • Electrical: 99.50%, 44 homes without a valid certificate. Of those, 22 have been out of date for more than a year, and the council says 21 of the long-standing cases are linked to hoarding or the condition of the property.
  • Asbestos and lifts: 100%
  • Decent Homes Standard: 98.48%, with 136 homes failing, down from 219
  • Damp and mould: 313 open cases, about 4% of homes. Nine were in the most serious category, and two of those went past 24 hours without the emergency work being recorded as done.

The council has been reporting these figures every month since the Regulator of Social Housing graded it C3 in September 2024. That is a non-compliant grade. We covered last month’s report when it went to Cabinet in October.

What it means for you

  • Council tenants get new legal rights from 30 November. The second phase of Awaab’s Law extends fixed repair deadlines from damp and mould to other hazards, including excess cold, falls, fire and electrical hazards, and pests.
  • The council’s own timescales under it: emergencies made safe within 24 hours, significant hazards investigated within 10 working days, and written findings within three working days of the investigation.
  • Letting contractors in matters. The report blames most of the remaining gas, electrical and lift gaps on homes where workers could not get access. If you have had a letter asking for an appointment, answering it keeps your home safe.
  • The decision is public. Cabinet meets at 7pm on Thursday 19 November at the Civic Centre, and the papers are on the council’s website.